Penhall details ongoing Port of Long Beach bridge demolition
Penhall Company →In a November 5, 2026 project update, Penhall described ongoing bridge demolition at the Port of Long Beach’s Pier B Shoemaker Bridge project. Its contracted work includes removing the existing 9th Street and 10th Street bridges, dismantling structural steel and taking out designated supports. The project uses three consecutive 55-hour weekend freeway closures for major demolition activities. Crews must coordinate equipment, debris processing and hauling while protecting infrastructure and bridge piers designated to remain. Penhall documented work during the September 26 weekend closure and described the assignment as an ongoing, multiphase project. The update also covers concrete cutting, substructure demolition and retaining wall removal.